Town Meeting

Back to Previous Warrant Articles To Top of Town Meeting Pages Ahead to Next Warrant Articles

CAPITAL IMPROVEMENT BUDGET ARTICLES

Articles 39 - 72 are the Capital Improvement Budget Articles as recommended by the Board of Selectmen in the FY 1999-2003 Capital Improvement Plan (CIP). A summary of potential capital projects for FY2000 - 2003 can be found in the Supplemental Information section of the Warrant.


ARTICLE 39:  APPROPRIATE FOR ROOF REPLACEMENT - HIGH SCHOOL

MOVED that the Town vote to raise and appropriate the sum of $575,000 to replace portions of the High School roof, to be spent under the direction of the Permanent Public Building Committee, and to meet this appropriation the Treasurer, with the approval of the Board of Selectmen is authorized to borrow up to $575,000 for a period of up to 20 years, under M.G.L. Chapter 44, Section 7.

Article 39 Explanation: A recently completed survey and evaluation of all school building roofs performed by a consultant engineer indicates the urgent need to replace many of the flat roof sections at the Needham High School. In most cases, the roof areas in question are not the original roofs, but either rubber membrane or polyvinyl chloride/plastic membrane replacement roof systems. These membrane roofs have expanded and contracted beyond their serviceable lives. They contain rips, tears and holes and are in a dangerously deteriorated condition in critical flashing and drainage areas. The risk associated with not repairing these roofs promptly is two-fold: (1) potential damage to the building structure and building contents and (2) potential threat to public safety from ceiling collapse in selected areas (e.g., the Auditorium).

Town Meeting Actions (5/13/98 9:38 pm -9:45 pm)

Disposition

Approved as amended

Amendments

  1. Matthews: Add emergency preamble and amend to $860,000.

    Aye

Discussion

Matthews. Some sections not done in 1488. Really all need repair now. Design has been done. Estimate was low. Preamble is so that it can be done this year.

Mr. Ryan. This number is reasonable and within their plans.


ARTICLE 40:  APPROPRIATE FOR ROOF REPLACEMENT - DPW BUILDING

MOVED that the Town vote to raise and appropriate the sum of $250,000 to replace the DPW roof, to be spent under the direction of the Permanent Public Building Committee, and to meet this appropriation the Treasurer, with the approval of the Board of Selectmen is authorized to borrow up to $250,000 for a period of up to 20 years, under M.G.L., Chapter 44, Section 7.

Article 40 Explanation: The roof on the DPW building failed in January 1998 following a storm. A roofing engineer was brought in to assess the roof and determine whether it should be repaired or replaced. The engineer recommended that the entire roof (23,160 square feet) be removed down to the structural deck and that a built up style roof be installed. This $250,000 estimate includes the cost for design specifications, construction and project management.

Town Meeting Actions (5/13/98 9:45 - 9:56 pm)

Disposition

Approved as amended

Amendments

  1. Owens: $275,000 instead of $250,000.

    Aye

Discussion

Mr. Owens. An emergency; not yet out for bid.

Culgen. Finance Committee approves.

Weitzen. Can temporary repairs be done. LaFleur. October, 1987 got 10-year warranty for rubber roof that failed in January, 1998. Need to remove roof to get at wet area. Can't patch that.

Tarallo. Can it be pumped. No.


ARTICLE 41:  APPROPRIATE FOR MECHANICAL SYSTEM REPAIR - HILLSIDE SCHOOL BOILER

MOVED that the Town vote to raise and appropriate the sum of $150,000 to replace the Hillside School boiler mechanical systems, to be spent under the direction of the Municipal Building Maintenance Board, and to meet this appropriation the Treasurer, with the approval of the Board of Selectmen is authorized to borrow up to $150,000 for a period of up to 20 years, under M.G.L., Chapter 44, Section 7.

Article 41 Explanation: At the FY97 Annual Town Meeting, $125,000 was appropriated for repair of the High School Boiler Feed System. This represented year one of a proposed four year plan to repair mechanical systems in school buildings. The Hillside boiler represents year two of that plan. At present, one of the two boilers at the Hillside School is inoperable. It was installed in 1961 and has reached its life expectancy. The school heating plant was designed to operate on a two boiler, "lead/lag" system. With one boiler inoperable, the remaining boiler (which was installed in 1988) is bearing a heating load that exceeds system design. The consequence will be to shorten the life of this functioning boiler. Further, if the existing functioning boiler shuts down there is no backup boiler to carry the heating load. If this occurred, the School would have to be shut down until the functioning boiler is repaired, or a temporary heating system can be installed.

Town Meeting Actions (5/13/98 9:57 pm -10:00 pm)

Disposition

Approved as amended

Amendments

  1. Emergency preamble and change amount to $200,000.

    Aye

Discussion

Matthews. Needs work now.

Paul Milligan. Will lead to efficiencies.

Ardini: Does it include disposal. Yes.


ARTICLE 42:  APPROPRIATE FOR ELEMENTARY SCHOOL ROOF REPAIRS

MOVED that the Town vote to raise and appropriate the sum of $60,000 for roof repairs, to be spent under the direction of the Municipal Building Maintenance Board, and to meet this appropriation the Treasurer, with the approval of the Board of Selectmen is authorized to borrow up to $60,000 for a period of up to 10 years, under M.G.L., Chapter 44, Section 7.

Article 42 Explanation: A recently completed roof survey and evaluation of all school building roofs performed by a consultant engineer indicates the need to make repairs to various components of all six elementary school building roofs. This project will address the following conditions found among the schools: missing and damaged flashing, membrane holes, damaged scuppers, damaged gravel stops, inadequate drains, and inadequate HVAC curb and sleeper tie-ins. It is recommended that all this work be done as one project because it should result in savings to the Town through a lower bid price than would occur if each school was bid separately over a number of years.

Town Meeting Actions (5/13/98 10:00 pm -10:04 pm)

Disposition

Approved

Aye

Discussion

Matthews. Series of roof repairs grouped for better price.

Milligan. Work to be held until fall for clearer picture of buildings' futures.

R. Sockol. Can these be grouped further? No; High School already bid. Other schools are too simple for big companies.


ARTICLE 43:  APPROPRIATE FOR MECHANICAL SYSTEM REPAIR - MITCHELL SCHOOL BOILER DESIGN SPECIFICATIONS

MOVED that the Town vote to raise and appropriate the sum of $18,000 for design specifications to replace the Mitchell School boiler mechanical systems, to be spent under the direction of the Municipal Building Maintenance Board, and to meet this appropriation the Treasurer, with the approval of the Board of Selectmen is authorized to borrow up to $18,000 for a period of up to five years, under M.G.L., Chapter 44, Section 7.

Article 43 Explanation: The #2 boiler is an eleven section cast iron steam boiler. It is 32 years old. It has reached its life expectancy which is evidenced by the facts that it runs rough, is very inefficient, and is extremely maintenance intensive. This project would entail the preparation of design specifications in order to replace the boiler and related mechanical systems in FY2000. The appropriation for the boiler replacement would be brought before the May 1999 Town Meeting.

Town Meeting Actions (5/13/98 10:04 pm - 10:07 pm)

Disposition

Approved as amended

Amendments

  1. Replace bonding language with ``from tax levy''.

    Aye

Discussion

Matthews. This is design work.

Milligan recommends acceptance.


ARTICLE 44:  APPROPRIATE FOR IMPROVEMENTS TO THE HIGH SCHOOL PARKING LOT

To see if the Town will vote to raise and appropriate the sum of $350,000 to resurface the High School parking lot; to be spent under the direction of the Municipal Building Maintenance Board, and to meet this appropriation the Treasurer, with the approval of the Board of Selectmen, is authorized to borrow up to $350,000 for a period of up to ten years under M.G.L. Chapter 44, Section 7; or take any other action relative thereto.

INSERTED BY: Board of Selectmen

FINANCE COMMITTEE RECOMMENDS THAT: Article Not be Adopted

Article 44 Explanation: An engineering firm recently completed a survey of certain school parking lots. In the study, the High School was noted as a high priority needing a variety of improvements at different areas on the site.. Conditions cited included the following: the main driveway and North Lot require a mill overlay due to cracking; the South lot is in very poor condition and requires the driveway and faculty lot to be reclaimed and paved; and, the concrete walkways around the school are in poor condition and require replacement. The price includes approximately $60,000 for traffic controls and alterations to insure the safety of pedestrians.

Town Meeting Actions

Disposition

Withdrawn by unanimous consent


ARTICLE 45:  APPROPRIATE FOR HIGH SCHOOL EXTRAORDINARY REPAIRS

MOVED that the Town vote to raise and appropriate the sum of $210,000 for extraordinary repairs to the high school exterior, to be spent under the direction of the Municipal Building Maintenance Board, and that to meet this appropriation the Treasurer, with the approval of the Board of Selectmen, is authorized to borrow up to $210,000 for a period of up to 20 years under M.G.L., Chapter 44, Section 7.

Article 45 Explanation: With the exception of the "A" Building, which was renovated in 1988, the High School exterior has not been painted in 20 years. In addition to this deferred maintenance, the paint has tested positive for lead. While funding for this project is being requested at the 1998 Annual Town Meeting, work will not be performed until the Summer of 1999 so as not to interfere with the proposed roofing work at the High School. The winter will be devoted to developing work specifications with the assistance of environmental engineering firm to insure compliance with lead rules. It is estimated that engineering services will cost $10,000.

Town Meeting Actions (5/13/98 5/13/98 -10:19 pm)

Disposition

Approved

Discussion

Matthews. Exterior Painting and remove lead.

Milligan. Supports.

Browne. Why so soon for summer 99 work. LaFleur - logistical nightmare; needs to be set up in spring

Saranbello. Speaks of 6 year old children in houses for lead paint. Answer; these are different concerns; have to barricade against scraped lead paint.

Sally Toran. Lots of ages use the High School.

Kensler. Is this price reasonable for level removal? They feel it is. Not full deleading.

Page. Have to deal with lead in a protective way.


ARTICLE 46:  APPROPRIATE FOR HIGH SCHOOL GYM RENOVATION DESIGN

To see if the Town will vote to raise and appropriate the sum of $10,000 for design specifications for renovations to the high school gym, to be spent under the direction of the Permanent Public Building Committee, and that to meet this appropriation the Treasurer, with the approval of the Board of Selectmen, is authorized to borrow up to $10,000 for a period of up to five years under M.G.L., Chapter 44, Section 7; or take any other action relative thereto.

INSERTED BY: Board of Selectmen

FINANCE COMMITTEE RECOMMENDS THAT: Article be Adopted, Funded from the Tax Levy

Article 46 Explanation: Prior to the October, 1996 rain storm, a capital request for renovation of the gym was submitted for funding. The conditions highlighted in that request as requiring attention were exacerbated by the October storm which caused the gym ceiling to collapse and warped the gym floor. While the floor was repaired, the ceiling has not been replaced. Further, the 1950's ventilation system requires upgrading and the poor lighting in the gym is barely acceptable for the interscholastic varsity sports program.

Town Meeting Actions (5/11/98 8:01 pm)

Disposition

Referred back to commitee

Discussion

Cogswell-Refer and transfer funds to reserve fund.


ARTICLE 47:  APPROPRIATE FOR HIGH SCHOOL AUDITORIUM RENOVATION SPECIFICATIONS

To see if the Town will vote to raise and appropriate the sum of $18,000 for design specifications for renovations to the high school auditorium, to be spent under the direction of the Permanent Public Building Committee, and that to meet this appropriation the Treasurer, with the approval of the Board of Selectmen, is authorized to borrow up to $18,000 for a period of up to five years under M.G.L., Chapter 44, Section 7; or take any other action relative thereto.

INSERTED BY: Board of Selectmen

FINANCE COMMITTEE RECOMMENDS THAT: Article be Adopted, Funded from the Tax Levy

Article 47 Explanation: The High School Auditorium was scheduled for renovation as part of the 1988 building renovation project at the High School. Due to unanticipated asbestos removal costs, the Auditorium work was dropped from the project. Many of the components of the auditorium have not been modified or upgraded since they were installed in 1930. This request is to prepare design specifications for refinishing the stage; re-upholstering 586 seats; replacing the stage curtain, door hardware and carpeting; painting the walls and ceiling, updating sound and light systems; and rehabilitating the ventilation system and temperature controls.

Town Meeting Actions (5/11/98 8:01 pm )

Disposition

Referred back to commitee

Discussion

Cogswell-Refer and transfer funds to reserve fund.


HomeTable of ContentsContact Us